What to do when a revised O&M manual arrives after the closeout is built
Keep a copy of the package you already sent, confirm the new revision applies to the installed equipment, then replace the file and rebuild. A newer manual is not automatically the right one, and a rebuilt PDF does not replace copies that have already gone out.
Before you change anything
- Save the closeout PDF and ZIP you sent, with the date sent, in your company's records folder. In Fast Closeouts, removing a file from a closeout deletes its current downloads, so keep your own copy of what went out first.
- Note who sent the revision, when, and what it says changed.
Confirm the revision applies
A revision can cover a different model, option set or production run. Ask the supplier which revision applies to the installed unit, and check your project requirements for how revised documents are resubmitted.
On federal work, UFGS 01 78 23 section 1.7.7 addresses manufacturer-originated changes or revisions to submitted data after the O&M data has been accepted, and sets a time frame for changes the Contracting Officer requests. It is a guide specification edited for each project. Your contract and the recipient's instructions set the actual process and deadline.
Replace the file and rebuild
The revised file counts toward the limits of 25 PDFs, 250 source pages and 20 MB per closeout.
- Open the saved closeout from your account and choose Edit and rebuild this closeout.
- Add the revised PDF. Remove the superseded one unless the recipient wants both.
- If adding the revised file would go over a job limit, remove the superseded file first, then add the revised one.
- Check the section and order. Give the document a title that includes the revision, such as AHU-01 O&M manual, Rev B.
- Rebuild. Revisions of the same closeout are included. Starting a new closeout instead counts as a separate closeout.
- Download the new PDF and ZIP. Copies you already sent are not replaced, so send the new package the way the recipient asks.
- If you use the document register, link the row to the revised PDF and mark it Checked again only after you confirm it applies.
What changes in the rebuilt PDF
Illustrative example with invented files. A closeout with a 1-page Rev A manual and a 1-page warranty was rebuilt after the manual was replaced by a 3-page Rev B.
| Measure | Before | After |
|---|---|---|
| Source PDFs | AHU-01_OM_RevA.pdf, AHU-01_Warranty.pdf | AHU-01_OM_RevB.pdf, AHU-01_Warranty.pdf |
| Source pages | 2 | 4 |
| Total PDF pages | 7 | 9 |
Check page references
The contents page and file list are rebuilt with the new page ranges, and documents after the replaced one move if the revised file has a different page count. Update any page numbers you quoted in a cover letter or transmittal.
Log the change
Record each revision in a short log: what arrived, what it replaced, whether it applies, and when the rebuilt package was sent. The second example row shows a newer revision that did not apply.
Related
See a sample closeout PDF, built from two public manufacturer manuals. Use the editable O&M index template to track your own records.
Combine up to 25 PDFs, 250 source pages and 20 MB per job. Saved to your account. Your first closeout is free, then $29 per additional closeout.
Choose PDFsPrepared with AI assistance. Fast Closeouts is not affiliated with the manufacturers or agencies cited.
Sources
- UFGS 01 78 23, Operation and Maintenance Data (May 2023, Change 4, August 2026). See section 1.7.7., Federal guide specification; project-specific requirements govern.
- Fast Closeouts help: return to a saved closeout, Current product instructions for saved closeouts and rebuilding.